Contract Date: 2025
Project Name & Location: Tradebe, Knowsley
Building / Structure / Area: Chemical Bund
Client: Tradebe
Specifier / Designer/ Architect / Engineer:
Main Products / Systems used: Remmers WHG Color
Project Summary: In 2025, our team was contracted by Tradebe, a leading waste management company, to enhance the chemical containment capabilities of their facility in Knowsley. The project involved applying the Remmers WHG system to a chemical bund to ensure compliance with environmental regulations and to prevent potential groundwater contamination.
The existing bund surface was cleaned and any defects were repaired to ensure optimal adhesion of the Remmers WHG system. The Remmers WHG coating was applied uniformly, creating a seamless and impermeable barrier. The system was allowed to cure as per the manufacturer’s guidelines to achieve maximum effectiveness.